Question: Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate
.png)
Status Report Ending Period 2 Task AC % Complete 75% Cumulative Totals Status Report Ending Period 4 Task % Complete 100% 100% Cumulative Totals Status Report Ending Period 6 Task % Complete 100% 100% 75% Cumulative Totals Status Report Ending Period 8 % Complete 100% 100% 100% 100% Cumulative Totals Performance Indexes Summary Period CPI PCI-B VAG =
Step by Step Solution
3.41 Rating (167 Votes )
There are 3 Steps involved in it
The project is performing nicely in terms of cost The project is currently 23 000 under budget and is getting 118 worth of work for each dollar spent ... View full answer