Question: Given the following project network, baseline, and status information, develop status reports for periods 2 , 4 , 6 , 8 and and complete the

Given the following project network, baseline, and status information, develop status reports for periods 2,4,6,8 and and complete the performance indexes table. Calculate the ()/((/mathrm{EAC}_(f)/)) and the ()/((/mathrm{VAC}_(()/(mathrm{f}))/).)
(Do not round intermediate calculations. Enter all answers to 2 decimal precision. Enter PCI-B in percent format (e.g., enter \(73.05\%\) if the decimal equivalent is 0.7305..)\begin{tabular}{|c|c|c|c|c|c|c|}
\hline \multicolumn{2}{|l|}{Status Report: Ending Period 4} & \multirow[b]{2}{*}{EV} & \multirow[b]{2}{*}{AC} & \multirow[b]{2}{*}{PV} & \multirow[b]{2}{*}{CV} & \multirow[b]{2}{*}{SV}\\
\hline Task & \% Complete & & & & & \\
\hline A & 100 & & 30.00 & & & \\
\hline B & 100 & & 23.00 & & & \\
\hline \multicolumn{2}{|l|}{Cumulative Totals} & & 53.00 & & & \\
\hline
\end{tabular}
\begin{tabular}{|c|c|c|c|c|c|c|}
\hline Status Report: Ending Period 6 & & & & & \\
\hline Task & \% Complete & EV & AC & PV & CV & SV \\
\hline A & 100 & & 30.00 & & & \\
\hline B & 100 & & 23.00 & & & \\
\hline C & 80.00 & & 25.00 & & & \\
\hline D & 0 & & 0.00 & & & \\
\hline E & 55.00 & & 8.00 & & & \\
\hline \multicolumn{2}{|l|}{ Cumulative Totals } & & 86.00 & & & \\
\hline
\end{tabular}
 Given the following project network, baseline, and status information, develop status

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!