Question: Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance indices table. Calculate the

Given the following project network, baseline, and status information, develop status reports for periods 5 and 10 and complete the performance indices table. Calculate the EACf and the VACf. Based on your data, what is your assessment of the current status of the project? At completion? Then answer the questions.

Given the following project network, baseline,

Given the following project network, baseline,

Given the following project network, baseline,

Given the following project network, baseline,

Given the following project network, baseline,

Question 1.

Based on your data, at the end of Period 5, the EV for Task A is equal to $________.

Group of answer choices:

1000

100

500

400

Question 2.

Based on your data, at the end of Period 5, the PV for Task A is equal to $________.

Group of answer choices:

500

1000

400

1200

Question 3.

Based on your data, at the end of Period 5, the CV for Task B is equal to $________.

Group of answer choices:

100

140

-140

-100

Question 4.

Based on your data, at the end of Period 5, the SV for Task A is equal to $________.

Group of answer choices:

300

-100

0

-300

Question 5.

Based on your data, at the end of Period 5, the cumulative total of CV is equal to $________.

Group of answer choices:

540

-540

60

-60

LEGEND ESID EF SL SL 2 B 8 8 D 12 LS DUR LF 0 0 0 0 2 6 8 8 8 4 12 0 A 0 NON 12 F 15 0 0 12 3 15 2. 2 2C7 7 E 10 2. 2 2 2 4 5 9 9 3 3 12 Project baseline (PV) (in $) B 8 9 Budget Task DUR ESLF SL (PV) 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 2 0 2 0 400 200 200 6 2 0 2400 200 600 200 600 200 600 600 200 5 2 2 1500 200 400 500 100 300 4 8 12 0 1600 400 400 400 400 12 2 900 300 400 200 3 12 15 0 600 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 6800 7000 7100 7400 D E 3 7 End of Period 5 EV Task Actual % Complete Finished AC $ 500 PV $ $ SV $ $ A B 40% 1100 80% 1500 D 0% 0 E 0% 0 F 0% 0 Cumulative Totals End of Period 10 PV Task Actual % Complete Finished EV $ AC $ 500 $ SV $ $ $ A B Finished 2300 Finished 1700 D 35% 600 E 100% 800 0 F 0% Cumulative Totals Performance Indices Summary (round to 2 decimal places) Period EV AC PV CPI SPI PCIB 5 10 EACE = VACt =

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!