Question: Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate
Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and complete the performance indexes table. Calculate the EACf and the VACf.

(Do not round intermediate calculations. Enter all answers to 2 decimal precision. Enter PCI-B in percent format (e.g., enter 73.05% if the decimal equivalent is 0.7305.)



\begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{2}{|c|}{ Status Report: Ending Period 2 } & & & & & \\ \hline Task & \% Complete & EV & AC & PV & CV & SV \\ \hline A & 75.00 & & 24.00 & & & \\ \hline B & 55.00 & & 12.00 & & & \\ \hline Cumulative Totals & & 36.00 & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \hline Status Report: Ending Period 4 & & & & & \\ \hline Task & % Complete & EV & AC & PV & CV & SV \\ \hline A & 100 & & 44.00 & & & \\ \hline B & 100 & & 21.00 & & & \\ \hline Cumulative Totals & & 65.00 & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c||} \hline \multicolumn{2}{|c|}{ Status Report: Ending Period 6 } & & & & & \\ \hline Task & \% Complete & EV & AC & PV & CV & SV \\ \hline A & 100 & & 44.00 & & & \\ \hline B & 100 & & 21.00 & & & \\ \hline C & 75.00 & & 22.00 & & & \\ \hline D & 0 & & 0.00 & & & \\ \hline E & 55.00 & & 12.00 & & & \\ \hline Cumulative Totals & & 99.00 & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|} \hline \multicolumn{2}{|c|}{ Status Report: Ending Period 8 } & & & & & \\ \hline Task & \% Complete & EV & AC & PV & CV & SV \\ \hline A & 100 & & 44.00 & & & \\ \hline B & 100 & & 21.00 & & & \\ \hline C & 100 & & 31.00 & & & \\ \hline D & 30.00 & & 18.00 & & & \\ \hline E & 100 & & 20.00 & & & \\ \hline Cumulative Totals & & & 134.00 & & & \\ \hline \end{tabular} Performance Indexes Summary \begin{tabular}{|c|c|c|c|c|c|c|c|} \hline Period & EV & AC & PV & SPI & CPI & PCl-B & \\ \hline 2 & & 36.00 & & & % \\ \hline 4 & & 65.00 & & & % \\ \hline 6 & & 99.00 & & & & % \\ \hline 8 & & 134.00 & & & & & \\ \hline \end{tabular} EACf=VACf=