Question: Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and and complete the performance indexes table.
Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8 and and complete the performance indexes table. Calculate the EACf and the VACf.
(Do not round intermediate calculations. Enter all answers to 2 decimal precision. Enter PCI-B in percent format (e.g., enter 73.05% if the decimal equivalent is 0.7305.)
| |||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |||||||||||||||||||||||||||||||||||||||||||||||||
EACf =
VACf =