Question: Given the following project network, baseline, and status information shown in Figure 2. Project Baseline (PV) (in RM) TaskDURES LFSL PV 0-11-22-3 3-4 4-5

Given the following project network, baseline, and status information shown in Figure2. Project Baseline (PV) (in RM) TaskDURES LFSL PV 0-11-22-3 3-4 4-5

Given the following project network, baseline, and status information shown in Figure 2. Project Baseline (PV) (in RM) TaskDURES LFSL PV 0-11-22-3 3-4 4-5 5-6 6-7 7-8 8-9 9-10 10-11 11-12 12-13 13-14-15 ABCDE 2020 800 400400 6 2802400 200 600 200 600 200 600 5 292 1500 200 400 500 100 300 4 8120 1600 400 400 400 400 3 7122 900 300 400 200 F 3 12150 600 14 200 100 300 Period PV total 200 200 4001000 700 700 500 900 800 600 400 400 200 100 300 Cumulative PV total 200/400800180025003200370046005400600064006800700071007400 (a) Figure 2 Complete the status reports for periods 4 and 8 in Table 1 below. (copy Table 1 to your answer box) [4 marks] Table 1 Status Report: Ending Period (5000) Task % complete EV AC PV 20 CV A 100% 300 B 50% 1000 C 33% 500 D 0% 0 E 0% 0 Cumulative Totals Status Report: Ending Period (5000) Task % complete EV AC PV A 100% 300 B 100% 2200 CV SV SV 95

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!