Question: Given the following project, reduce its duration as much as possible, at the lowest cost using the Siemens Approximate Method (SAM). The indirect cost is

Given the following project, reduce its duration as much as possible, at the lowest cost using the Siemens Approximate Method (SAM). The indirect cost is $ 200.00 per day.

ACTIVITY PREVIOUS ACTIVITY DURATION (DAYS) COST $ MINIMUM DURATION $ PER UNIT REDUCED DAYS TO REDUCE
A - 10 1000 7 70 3
B - 12 1000 6 90 6
C A 8 1500 3 50 5
D A 24 2000 13 100 11
E C,B 20 2500 14 120 6