Question: Given the following project, reduce its duration as much as possible, at the lowest cost using the Siemens Approximate Method (SAM). The indirect cost is
Given the following project, reduce its duration as much as possible, at the lowest cost using the Siemens Approximate Method (SAM). The indirect cost is $ 200.00 per day.
| ACTIVITY | PREVIOUS ACTIVITY | DURATION (DAYS) | COST $ | MINIMUM DURATION | $ PER UNIT REDUCED | DAYS TO REDUCE |
| A | - | 10 | 1000 | 7 | 70 | 3 |
| B | - | 12 | 1000 | 6 | 90 | 6 |
| C | A | 8 | 1500 | 3 | 50 | 5 |
| D | A | 24 | 2000 | 13 | 100 | 11 |
| E | C,B | 20 | 2500 | 14 | 120 | 6 |