Question: Given the following sensitivity analysis for a new project, answer the questions below 1. What is the expected NPV in $000,000s? a. 49 b. 18
Given the following sensitivity analysis for a new project, answer the questions below

1. What is the expected NPV in $000,000s?
a. 49 b. 18 c. -2 d. Can Not Be Determined
2. What is the expected NPV if the Projects Variable Cost were 20% higher than Base (expected)?
-20 b. -38 c. -92 d. None
3. Which input variable would cause you the most concern?
Units Sold b. Cost of Capital c. Variable cost d. Price per Unit
CHANGE FROM NPV(IN$000,000 'S) BASE LEVEL (\%) \begin{tabular}{ccc} \hline UNITS SOLD & VARIABLE COST/UNIT & PRICE/UNIT \\ \hline-2 & 100 & -160 \\ 11 & 80 & -145 \\ 18 & 68 & -92 \\ 49 & 49 & 49 \\ 77 & -20 & 89 \\ 88 & -38 & 153 \\ 102 & -88 & 172 \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
