Question: Sensitivity Analysis Given the following sensitivity analysis for a new project, answer the questions below: CHANGE FROM _________________ NPV (IN $000,000S)________________ BASE LEVEL (%) UNITS

Sensitivity Analysis

Given the following sensitivity analysis for a new project, answer the questions below:

CHANGE FROM _________________NPV (IN $000,000S)________________

BASE LEVEL (%) UNITS SOLD VARIABLE COST/UNIT PRICE/UNIT

-40% -2 100 -160

-20% 11 80 -145

-10% 18 68 -92

0% 49 49 49

+10% 77 -20 89

+20% 88 -38 153

+40% 102 -88 172

16. What is the expected NPV in $000,000s?

a. 49 b. 18 c. -2 d. Can Not Be Determined

17. What is the expected NPV if the Projects Variable Cost were 20% higher than Base (expected)?

-20 b. -38 c. -92 d. None

18. Which input variable would cause you the most concern?

Units Sold b. Cost of Capital c. Variable cost d. Price per Unit

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!