Question: Given the following table: Activity Immediate Predecessor Time(days) A 4-5-6 3-4-8 1-2-5 5-6-9 A C D E F A B B. CE D.F. GHI 2.3-6

Given the following table: Activity Immediate Predecessor Time(days) A 4-5-6 3-4-8 1-2-5 5-6-9 A C D E F A B B. CE D.F. GHI 2.3-6 4-5-6 G HI Finish Calculate the expected duration for activity B. Select one: a.5 days b.none of the above c.6.5 days d.4.5 days e.6 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
