Question: Given the following table: Activity Immediate Predecessor Time(days) A 4-5-6 3-4-8 1-2-5 5-6-9 A C D E F A B B. CE D.F. GHI 2.3-6

Given the following table: Activity Immediate

Given the following table: Activity Immediate Predecessor Time(days) A 4-5-6 3-4-8 1-2-5 5-6-9 A C D E F A B B. CE D.F. GHI 2.3-6 4-5-6 G HI Finish Calculate the expected duration for activity B. Select one: a.5 days b.none of the above c.6.5 days d.4.5 days e.6 days