Question: Given the following table. Immediate Predecessor Time(days) Activity A B C D E F A 4.5-6 3.4.8 1-2-5 5-6-9 2-3-4 2-3-6 4-5-6 3-4-8 B G

Given the following table. Immediate Predecessor Time(days) Activity A B C D E F A 4.5-6 3.4.8 1-2-5 5-6-9 2-3-4 2-3-6 4-5-6 3-4-8 B G B C.E D.F G.H H Finish Calculate the variance for activity D Select one: a.0.65 b.0.62 c.0.44 d.0.52 e. 0.11
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
