Question: Given the following table, use the CPM technique to draw the network diagram and answer below questions. Activity Optimistic Time Most Likely Time Pessimistic Time
Given the following table, use the CPM technique to draw the network diagram and answer below questions.
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time | Immediate Predecessor Activities |
| a | 10 | 22 | 28 |
|
| b | 12 | 24 | 30 |
|
| c | 6 | 12 | 18 |
|
| d | 4 | 16 | 34 | a |
| e | 8 | 8 | 20 | a,b,c |
| f | 8 | 14 | 20 | a,b,c |
| g | 4 | 4 | 4 | a,b,c |
| h | 4 | 14 | 18 | c |
| i | 6 | 16 | 38 | g,h |
| j | 4 | 10 | 16 | d,e |
Critical Path:
1/ c,h,i
2/ a,d,j
3/ a,e,j
4/ b,e,j
The project Critical Time:
a.41 days
b.43 days
c.45 days
d.48 days
Calculate the total float and free float of activity (e)
a.0 days free float and 0 days total float
b.5 days free float and 0 days total float
c.0 days free float and 5 days total float
d.5 days free float and 5 days total float
Step by Step Solution