Question: Given the following table, what is the probability that the project will take more than 32 days to complete. Use 2 decimals for your calculations

Given the following table, what is the probability that the project will take more than 32 days to complete. Use 2 decimals for your calculations and choose the nearest answer. a. 0.75 b. 0.56 C. 0.17 d. 0.83