Question: Given the following task time estimates ( days ) Task Time Predecessor A 1 9 - - B 1 2 - - C 9 -

Given the following task time estimates (days) Task Time Predecessor A 19-- B 12-- C 9-- D 12 A E 20 B, C F 14 D, E G 28 D H 15 F I 18 G, H a. What is the critical path? [Blank1] b. What is the project length? [Blank2] days c. How much slack in task B.?[Blank3] days d. How much slack is in task A.?[Blank4] days e. What is the early start / early finish for task F.?[Blank5],[Blank6] days days f. What is the late start / late finish for task G.?[Blank7],[Blank8] g. What if task A increased by 2 days. What would be the project length and the critical path? [Blank9]