Question: Given the following task time estimates ( days ) TaskTimePredecessorA 1 9 - - B 1 2 - - C 9 D 1 2 AE
Given the following task time estimates days
TaskTimePredecessorABCDAEB CFD EGDHFIG H
a What is the critical path? Select C E F H I", B C F H I", A D E F G I", B E F H I", A C D G
b What is the project length? Select days", days", days", days", days"
c How much slack in task B Select zero it is on the critical path",
d How much slack is in task A Select day", "zero it is on the critical path", days", days", days"
e What is the early start early finish for task F Select and and and and and
f What is the late start late finish for task G Select and and and and and
g What if task A increased by days. What would be the project length and the critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
