Question: Given the following task time estimates ( days ) TaskTimePredecessorA 1 9 - - B 1 2 - - C 9 D 1 2 AE

Given the following task time estimates (days)
TaskTimePredecessorA19--B12--C9D12AE20B, CF14D, EG28DH15FI18G, H
a. What is the critical path? [ Select ]["C, E, F, H, I", "B, C, F, H, I", "A, D, E, F, G, I", "B, E, F, H, I", "A, C, D, G"]
b. What is the project length? [ Select ]["75 days", "83 days", "79 days", "91.5 days", "72.5 days"]
c. How much slack in task B.?[ Select ]["4","3","0(zero), it is on the critical path", "2","1"]
d. How much slack is in task A.?[ Select ]["1 day", "zero - it is on the critical path", "3 days", "15 days", "8 days"]
e. What is the early start / early finish for task F.?[ Select ]["20 and 34","32 and 46","0 and 14","61 and 79","19 and 31"]
f. What is the late start / late finish for task G.?[ Select ]["33 and 61","46 and 61","31 and 59","20 and 32","12 and 32"]
g. What if task A increased by 2 days. What would be the project length and the critical path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!