Question: Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D
Given the following task time estimates (HOURS),
| Task | Time | Predecessor |
| A | 40 | |
| B | 20 | |
| C | 25 | A |
| D | 19 | A, B |
| E | 25 | C, D |
| F | 24 | E |
| G | 18 | F |
a. How long is the project length? [ Select ] ["134.83", "122.00", "127.45", "135.78", "132.00"] .
b. What tasks form the critical path? [ Select ] ["B, C, D, E, F, G", "A, B, C, E, F, G", "B, D, E, F, G", "A, D, E, F, G", "A, C, E, F, G"]
c. What is the LS/LF for activity D.? [ Select ] ["65 and 90", "44 and 55", "34.56 and 4.78", "50.19 and 7.08", "46 and 65"] .
d. How much slack is there in activity C? [ Select ] ["8.34 hours", "29 hours", "6 hours", "0", "12 hours"]
How much slack in activity D? [ Select ] ["5 hours", "26 hours", "0, it is on the critical path", "28 hours", "6 hours"]
e. What if activity D. was delayed by 6 hours, what would be the project length and critical path? [ Select ] ["133 hours; A, C, E, F, G", "132 hours; B, C, D, E, F, G", "132 hours; A, C, D, E, F, G", "130 hours; B, C, E, F, F", "no change in either the critical path or project length"]
f. Referring to letter e., how much slack would be in activity B.? [ Select ] ["8 hours", "26 hours", "0 (zero), it is now on the critical path", "6 hours", "20 hours"]
Please provide in depth instructions with explanations. Thank you.