Question: Given the following tasks data for a project, table [ [ Task Label,Predecessor,Duration ( weeks ) ] , [ A , - , 5

Given the following tasks data for a project,
\table[[Task Label,Predecessor,Duration (weeks)],[A,-,5],[B,-,3],[C,-,4],[D,A,1],[E,B,2],[F,B,5],[G,B,9],[H,C,D,E,4],[I,F,2]]
a. Draw the CPM network (AON) diagram
I. Determine the earliest start and latest start, earliest finish and latest finish times for each task. Use the following format to draw the network diagram and to present your answers.
-Earliest start = maximum EF of immediate predecessors EF=ES+t
-Latest finish = minimum of latest start of following activities LS=LF-t
II. Identify the total slack, free slack, safety slack, and independent slack for each task.
III. Determine the critical path.
IV. Determine the minimum project completion time.
b. Draw the Gantt chart
I. Determine the project completion time.
II. Determine each task's total slack.
 Given the following tasks data for a project, \table[[Task Label,Predecessor,Duration (weeks)],[A,-,5],[B,-,3],[C,-,4],[D,A,1],[E,B,2],[F,B,5],[G,B,9],[H,C,D,E,4],[I,F,2]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!