Question: Given the following tasks, durations and dependencies Task Duration (weeks) Predecessors A 2 None B 3 None C 1 A D 4 A E 5
Given the following tasks, durations and dependencies
| Task | Duration (weeks) | Predecessors |
| A | 2 | None |
| B | 3 | None |
| C | 1 | A |
| D | 4 | A |
| E | 5 | B |
| F | 6 | A, D |
| G | 2 | A, E |
| H | 4 | F |
| I | 2 | G,H |
Create a Gantt chart. How many weeks will it take to complete the project?
Create a PERT chart. What is the critical path?