Question: Given the following tasks. Task Duration (Days) Task Dependencies A 5 - B 2 A C 4 A D 10 B, C What is the

Given the following tasks.

Task

Duration (Days)

Task Dependencies

A

5

-

B

2

A

C

4

A

D

10

B, C

What is the free float for task B?

  1. 1
  2. 2
  3. 4
  4. 7