Question: Given the following tasks for a small project, perform a CPM analysis to determine: a) project duration b) slack for each task c) the set

Given the following tasks for a small project, perform a CPM analysis to determine:

a) project duration

b) slack for each task

c) the set of tasks on the critical path

begin{tabular}{|l|l|l|} hline Task & Predecessors & Duration  hline A & & 3  hline B & A & 2  hline C & A,B & 5
 

Task A B C D E F Predecessors A A,B C, B C D,E Duration 3 2 5 6 3 7