Question: Given the following information on a small project: A is the first activity of the project and precedes the activities B and C. The activity
Given the following information on a small project: A is the first activity of the project and precedes the activities B and C. The activity D succeeds both B and C whereas only C is required to start activity E. D precedes F while G succeeds E. H is the last activity of the project and succeeds F and G. Draw a network based on this information.