Question: Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for

Given the forecast and booked orders shown in the

Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for period 3? 1 70 80 2 65 50 3 60 30 4 70 10 Period Forecasted Demand Booked Orders Projected ending inventory Master production schedule Available to Promise 55 0 60 10 55 70