Question: Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for

Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for period 4?

Period 1 2 3 4
Forecasted Demand 70 65 60 75
Booked Orders 80 50 30 20
Projected ending inventory
Master production schedule 55
Available to Promise 0