Question: Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for
Given the forecast and booked orders shown in the table, and a beginning inventory of 25, what should the master production schedule quantity be for period 4?
| Period | 1 | 2 | 3 | 4 |
| Forecasted Demand | 70 | 65 | 60 | 75 |
| Booked Orders | 80 | 50 | 30 | 20 |
| Projected ending inventory | ||||
| Master production schedule | 55 | |||
| Available to Promise | 0 |