Question: Given the information below: a . This project will be completed in days. b . Is task A critical? ( Type yes or no )

Given the information below:
a. This project will be completed in
days.
b. Is task A critical? (Type yes or no):
c. Task B has a total float of
days.Activity Immediate Predecessors Duration (days)
A -5
B -6
C -3
D C 2
E A 5
F B, D 10
G C 7