Question: Activity Immediate Predecessors Duration (days) A - 5 B - 6 C - 3 D C 2 E A 10 F B, D 6 G
| Activity | Immediate Predecessors | Duration (days) |
|---|---|---|
| A | - | 5 |
| B | - | 6 |
| C | - | 3 |
| D | C | 2 |
| E | A | 10 |
| F | B, D | 6 |
| G | C | 7 |
Given the information above:
1. This project will be completed in how many days?
2. Is taks A critical?
3. Task F has a total float of how many days?