Question: . Given the information below, determine the average tardiness using SPT. (round off your answer to nearest whole number) Processing Time (Hrs.) 17 10
. Given the information below, determine the average tardiness using SPT. (round off your answer to nearest whole number) Processing Time (Hrs.) 17 10 5 7 Job A B C D E 11 Hour Due 15 25 20 32 38
Step by Step Solution
3.43 Rating (156 Votes )
There are 3 Steps involved in it
JOB SEQUENCE Job sequence is obtained by ranking the j... View full answer