Question: Given the information below, determine the following: (i) Processing sequence using (1) SPT and (2) EDD. (ii) Average flow time and average job lateness using

Given the information below, determine the following: (i) Processing sequence using (1) SPT and (2) EDD. (ii) Average flow time and average job lateness using (1) SPT and (2) EDD. Job Processing Time (hours) Hour (due) A 17 15 B 10 25 C 5 20 D 7 32 E 11 38