Question: Given the information below, determine the following: Job Processing Time (hrs) Hour Due A 17 15 B 10 25 C 5 20 D 7 32
Given the information below, determine the following:
| Job | Processing Time (hrs) | Hour Due |
| A | 17 | 15 |
| B | 10 | 25 |
| C | 5 | 20 |
| D | 7 | 32 |
| E | 11 | 38 |
I need help with only this question and its not -1.6: What is the average job tardiness by using SPT? (Fill in only number, no unit.)