Question: Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that
Given the information below, estimate the probability that the noncritical path B-C-G will take more than 15 weeks. Hint: Subtract from 1.0 the probability that B-C-G will take 15 weeks or less. Refer to the standard normal table Expected Time (weeks) Variance A 4.5 1.25 B 5.5 0.69 C 3.5 0.15 D 12.0 1.78 E 6.0 2.40 F 8.5 3.04 G 4.5 0.49 The probability that this path will take more than 15 weeks to complete is enter your response here . (Enter your response rounded to four decimal places.)