Question: Given the information below, how long is the Critical Path? table [ [ Activity , Time,Predecessor ] , [ A , 2 , ]
Given the information below, how long is the Critical Path?
tableActivityTime,PredecessorABCADBECDFDGCHGEIEFSHI