Question: Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the

Given the information below: (Use normal time to calculate original path)

a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days?

b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days?

c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days?

d) What is the total cost to reduce the project from the original normal completion time to 19 days?

Activity Immediate Predecessors Normal time Crash time Normal cost Crash cost
A - 5 3 $3,000 $3,600
B - 6 4 $3,500 $4,300
C A 7 5 $3,300 $4,000
D B 5 4 $2,200 $2,400
E B 3 2 $1,700 $2,200
F D,E 5 3 $2,200 $3,600
G C,D 7 6 $1,900 $2,550
H F,G 3 2 $1,200 $1,750

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!