Question: Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the
Given the information below: (Use normal time to calculate original path)
a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days?
b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days?
c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days?
d) What is the total cost to reduce the project from the original normal completion time to 19 days?
| Activity | Immediate Predecessors | Normal time | Crash time | Normal cost | Crash cost |
| A | - | 5 | 3 | $3,000 | $3,600 |
| B | - | 6 | 4 | $3,500 | $4,300 |
| C | A | 7 | 5 | $3,300 | $4,000 |
| D | B | 5 | 4 | $2,200 | $2,400 |
| E | B | 3 | 2 | $1,700 | $2,200 |
| F | D,E | 5 | 3 | $2,200 | $3,600 |
| G | C,D | 7 | 6 | $1,900 | $2,550 |
| H | F,G | 3 | 2 | $1,200 | $1,750 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts