Question: Given the information in the Table below: a. What is the shortest time in which the project can be completed? b. What are the critical

Given the information in the Table below: a. What
Given the information in the Table below: a. What is the shortest time in which the project can be completed? b. What are the critical activities? c. Pick a non-critical path. What is the probability that this path being critical? d. What is the standard deviation of the critical path? e. What is the probability that the project will be completed in 20 weeks? Duration (weeks) Activity Optimistic Most Pessimistic Preceding activities likely A 1 2 3 B 3 5 11 A C 5 7 9 A D 5 7 12 B E 1 2 3 C F 7 9 11 G 2 3 4 D, E