Question: given the information in the table below apply project analytical tools to calculate the following 1. find each activity ES, EF, LS and LF 2.
given the information in the table below apply project analytical tools to calculate the following
1. find each activity ES, EF, LS and LF 2. identify all paths 3. which path is the critical path 4. calculate the slack for each activity
Activity duration predecessor
A 6None B 8A C 6A D 4C E 6B F 7B,D G 5C H 6F,G I 4E,H