Question: Given the information listed in table below, use the template provided to construct a project network diagram for the stadium project, displaying activity ID, duration,

Given the information listed in table below, use the template provided to construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish.

Answer the following questions:

How many working days will the project take?

What is the critical path for the project?

Read and complete the Ventura Baseball Stadium case below.

VENTURA BASEBALL STADIUM

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on June 10, 2019 and be completed by April 3, 2022, in time for the start of the 2022 season.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $5 million on the project. He also said that if they were successful, the prospects of future projects would be bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ID Activity Duration Predecessor(s)
1 Baseball Stadium
2 Clear stadium site 60 days
3 Demolish building 30 days 2
4 Set up construction site 30 days 2
5 Drive support piling 120 days 2
6 Pour lower concrete bowl 120 days 5
7 Pour main concourse 120 days 4, 6
8 Install playing field 90 days 4, 6
9 Construct upper steel bowl 120 days 4, 6
10 Install seats 140 days 7, 9
11 Build luxury boxes 90 days 7, 9
12 Install jumbotron 30 days 7, 9
13 Stadium infrastructure 120 days 7, 9
14 Construct steel canopy 75 days 10
15 Light installation 30 days 14
16 Build roof supports 90 days 6
17 Construct roof 180 days 16
18 Install roof tracks 90 days 16
19 Install roof 90 days 17, 18
20 Inspection 20 days 8, 11, 13, 15, 19

Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish. NOTE: Copy-paste and fill in the 3x3 cell set to create building blocks for your project network diagram. Given the information listed in table below, use the template provided toconstruct a project network diagram for the stadium project, displaying activity ID,

What is the critical path for the project? (Enter response)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!