Question: Given the information listed in table below, use the template provided to construct a project network diagram for the stadium project, displaying activity ID, duration,

Given the information listed in table below, use the template provided to construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish.

Answer the following questions:

  • How many working days will the project take?
  • What is the critical path for the project?

Read and complete the Ventura Baseball Stadium case below.

VENTURA BASEBALL STADIUM

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on June 10, 2019 and be completed by April 3, 2022, in time for the start of the 2022 season.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $5 million on the project. He also said that if they were successful, the prospects of future projects would be bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

IDActivityDurationPredecessor(s)
?1Baseball Stadium

?2Clear stadium site?60 days?
?3Demolish building?30 days2
?4Set up construction site?30 days2
?5Drive support piling120 days2
?6Pour lower concrete bowl120 days5
?7Pour main concourse120 days4, 6
?8Install playing field?90 days4, 6
?9Construct upper steel bowl120 days4, 6
10Install seats140 days7, 9
11Build luxury boxes?90 days7, 9
12Install jumbotron?30 days7, 9
13Stadium infrastructure120 days7, 9
14Construct steel canopy?75 days10
15Light installation?30 days14
16Build roof supports?90 days6
17Construct roof180 days16
18Install roof tracks?90 days16
19Install roof?90 days17, 18
20Inspection?20 days8, 11, 13, 15, 19


When you open the image, the excel instructions are:

Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish. NOTE: Copy-paste and fill in the 3x3 cell set to create building blocks for your project network diagram.

PMT472L 2.2 CASE STUDY: VENTURA BASEBALL STADIUM - PART A Project NetworkDiagram Construct a project network diagram for the stadium project, displaying activity


PMT472L 2.2 CASE STUDY: VENTURA BASEBALL STADIUM - PART A Project Network Diagram Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish 2 0 ? ? ES ID EF SL SL LS DUR LF 60 60 ? ?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Law Questions!