Question: Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path. Lag 1 D E Build Install
Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path.

Lag 1 D E Build Install Cabinets Cabinets 7 2 A Lag 5 Design B 3 Tear Down 3 F G Lag 2 Install Appliances Inspect C 2 1 Lag 5 Order Legend Appliances ES 10 EF SL Description SL LS Duration LF