Question: Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path. Lag 1 Build Install Cabinets Cabinets
Given the network below, compute the early, late, and slack time for each activity. Clearly identify the critical path.
.png)
Lag 1 Build Install Cabinets Cabinets A Lag 5 Design B Tear Down 3 Install Appliances Inspect Lag 2 2 Lag 5 Order Legend Appliances ES EF 10 SL Description SL LS LF Duration
Step by Step Solution
3.42 Rating (168 Votes )
There are 3 Steps involved in it
The critical path is ADEFG 0 0 0 A Design 3 Lag 2 3 0 3 Legend ... View full answer