Question: Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are optimistic

Given the network diagram below, determine the

Given the network diagram below, determine the probability that the project will finish within 26 weeks of its start. Times on the diagram are optimistic times, most likely times, and pessimistic times in weeks. 10-16-22 1-4-7 2-5-8 1-1-1 9-10-15 4-6-8 3-5-7 5-8-13

Step by Step Solution

There are 3 Steps involved in it