Question: A certain project has the following precedence relationships. Activity Immediate Predecessor(s) A - B - C - D A, B E B F C, E
A certain project has the following precedence relationships.
| Activity | Immediate Predecessor(s) |
|---|---|
| A | - |
| B | - |
| C | - |
| D | A, B |
| E | B |
| F | C, E |
| G | D, E |
| H | F, G |
1)Draw the network diagram
2)What are the paths, from start to finish?
The activity times, in three different estimates (optimistic, most likely, and pessimistic), are as follows.
| Activity | Optimistic (a) | Most Likely (m) | Pessimistic (b) |
|---|---|---|---|
| A | 2 | 6 | 9 |
| B | 6 | 10 | 12 |
| C | 4 | 9 | 15 |
| D | 5 | 5 | 8 |
| E | 2 | 6 | 12 |
| F | 5 | 8 | 9 |
| G | 3 | 4 | 6 |
| H | 4 | 6 | 8 |
3)What is the expected time (te) for each activity? Round your calculations to the nearest second decimal point. Show all your work.
4)What is the critical path, and how long is this project expected to last? Show all your work.
5)What is the variance of the critical path? Round your calculations to the nearest second decimal point. Show all your work.
6)Suppose you have a personal goal of completing this project in 31 weeks,
What is the probability that you will be able to meet this goal? Round your analysis to the nearest second decimal point. Show all your work.