Question: Given the network plan that follow 5 , compute the early, late, and slack times. What is the project duration? The time - constrained length
Given the network plan that follow compute the early, late, and slack times. What is the project duration?
The timeconstrained length of the
project is:
Without regard to resources, what is the slack for:
Using any approach you wish eg trial and error develop a loading chart for resources carpenters iCl and electricians
E Assume only one carpenter is avallable and two electricians are avallable.
Given your resource schedule, compute the eary, late, and slack times for your project. What is the project duration now?
now?
The project
duration
Which activities are now critical? You may select more than one answer, Single click the box with the question mark
a wrong answer. Any boxes left with answer and double click the box with the question mark to empty the box for
a wrong answer. Any boxes left with a question mark wili be automatically graded as incorrect.
Step by Step Solution
There are 3 Steps involved in it