Question: Given the network plan that follows, develop a resource requirement plan. Calculate the total resource load per day in the bottom row. Resource Requirement Plan

Given the network plan that follows, develop a resource requirement plan.

Calculate the total resource load per day in the bottom row.

Given the network plan that follows, develop a

Resource Requirement Plan
Task 0 - 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 - 15 - 16
A
B
C
D
E
F
G
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Resources

Use the table below or Excel file to show your calculations:

Resource Requirement Plan
Task 0 - 1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 - 15 - 16
A
B
C
D
E
F
G
Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Resources

Question 29

What is the project's critical path?

a.

A-B-D-F

b.

A-B-C-F

c.

A-B-E-F

Question 30

Considering your computations in the previous question, what is the maximum number of resources required on the project daily?

Answer:

Question 31

Considering your computations in the previous question, what is the minimum number of resources required on the project daily?

Answer:

Question 28 Not yet answered Given the network plan that follows, develop a resource requirement plan. Calculate the total resource load per day in the bottom row. Marked out of 9 13 4.0 P Flag question 1 1 1 10 4 14 4 B 9 9 D 14 14 TI 16 OOO A 4 0 2 0 4 4 0 2 0 0 2 0 0 2 0 4 5 9 9 5 14 14 2 16 9 E 12 ES ID EF 2 1 2 SL RES SL 11 3 14 LS DUR LF Resource Requirement Plan Task 0 - 11 2 31- 41- 5- 61 7 81- 9 - 10- 11 121- 13 14 15 16 A B D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!