Question: Given the network shown above, what is the earliest start time for activity G ? Question 7 Answer a . 2 1 b . 2

Given the network shown above, what is the earliest start time for activity G?
Question 7 Answer
a.
21
b.
22
c.
24
d.
29
e.
26Use the following to answer questions 6-10:
The activities described by the following table are given for the Howard Corporation in Kansas:
\table[[Activity,\table[[Time],[(in weeks)]],\table[[Immediate],[predecessor(s)]]],[A,8,-],[B,6,A],[C,6,A],[D,7,B],[E,8,B],[F,10,C],[G,5,E, F],[H,5,D],[I,3,G, H]]
 Given the network shown above, what is the earliest start time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer