Question: Given the network shown below - Bla) A(2) D(6) * C12) 14. What is the earliest start time for activity D? A. 4 B. 5

Given the network shown below - Bla) A(2) D(6) *
Given the network shown below - Bla) A(2) D(6) * C12) 14. What is the earliest start time for activity D? A. 4 B. 5 C. 6 D. 12 ou 15. What is the slack time for activity B? A. 0 B. 2 C. 3 D. 4 E. 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock