Question: Given the operation times provided: a. Develop a job sequence that minimues idle time at the two work centers. b. Construct a chart of the

Given the operation times provided: a. Develop a
Given the operation times provided: a. Develop a job sequence that minimues idle time at the two work centers. b. Construct a chart of the activities at the two centers, and determine each one's idle time, assuming no other activities are involved. JOB TIMES (minutes) A 20 35 Center 1 Center 2 16 30 60 12 27 51 28 24