Question: Given the order-requirement digraph shown (with time given in minutes) and the priority list T6, T5, T4, T3, T2, T1, apply the list-processing algorithm
Given the order-requirement digraph shown (with time given in minutes) and the priority list T6, T5, T4, T3, T2, T1, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require? T T2 T3 5 3 T5 T6 8 7 T4 3
Step by Step Solution
There are 3 Steps involved in it