Question: Given the order - requirement digraph below ( with time given in minutes ) and the priority list T 1 , T 2 , T

Given the order-requirement digraph below (with time given in minutes) and the priority list T1,T2,T3,T4,T5,T6,T7, apply the list-processing algorithm to construct a schedule using two processors. How much time does the resulting schedule require?
 Given the order-requirement digraph below (with time given in minutes) and