Question: Given the precedence network given above: a) Find the schedule dates ESD,EFD,LSD,LFD for each activity b) calculate the lag for each link: A-B, A-C, A-D

Given the precedence network given above:
a) Find the schedule dates ESD,EFD,LSD,LFD for each activity

b) calculate the lag for each link:
A-B, A-C, A-D , B-E, B-F, C-F, C-G, D-H, E-J, F-J, F-K, G-J, G-K, G-L, H-K, H-L, J-M, K-M, K-N, L-M ,L-N, M-P, N-P
c) Find the floats TF, FF for each activity
d) Which network path is the critical path?