Question: Given the product structure below, develop an MPS, and MRP plans of 8 weeks planning period, product A is scheduled for delivery at week

Given the product structure below, develop an MPS, and MRP plans of 8 weeks planning period, product A is scheduled for delivery at week 8. If the ask you to deliver half of the patch a week 4 how this will change the MRP plan Given the following bill of material 1. C (1) B(2) D (1) D (1) A C (3) E (2) D (1) F (1) G (2) * the demand for product A is 50 units Lead time A is one week, B is 2 weeks, C 1 week, D is one week, E is two weeks,F is 3 weeks, G is two weeks
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
Answer To develop an MPS Master Production Schedule and MRP Material Requirements Planning plan well follow these steps 1 Master Production Schedule M... View full answer