The following represents a project that should be scheduled using CPM:
.png)
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16days?
TiMES (DAYS) ACTIVITY IMEDIATE PREDECESSORS PN 4 C, D D E FG 4 4 5
Step by Step Solution
3.35 Rating (182 Votes )
There are 3 Steps involved in it
a TIMES DAYS ACTIVITY IMMEDIATE PREDECESSORS a m b E0054 s 2 A 1 3 5 3 04444 B 1 ... View full answer