Question: Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID)Description PrecedingActivity Time Activit None UR)

Given the project activity information provided below: a) Draw the project network. b) What is the critical path? Activity (ID)Description PrecedingActivity Time Activit None UR) (days 40 30 10 15 Requirements Architecture Desi Desi Design M Coding Coding T Coding N Integration I Integration J System 4 4,5 4 6,7 7,8 9,10 10 4 12